Structural Audit and Assessment
HUB Power Station, Karachi
Zor Engineers were commissioned to examine parts of the power station that were suffering from severe corrosion, including the intake dam, boiler foundations, outlet channel, and approximately 400 residential, workshop and storage buildings. Zor prepared a detailed report son the cause and extent of the damage. Following this, Zor was commissioned by the client to develop solutions to address structural deterioration of some of the most critical structures.
Reference: Pir Wali Shah, Senior Engineer (Civil)
Location
Karachi
Category
Residential & Commercial
Date
—
Project Value
—








